HVC 450 kW E-Bus Charger Installation Guide
This extra cable length is required to connect the AC power cable with
the connectors in the Power Cabinet without problems.
11. Place both cover plates on the appropriate place on the foundation.
12. Secure the top cover plate with M16 bolts (4x) and the front cover plate with M12 bolts
(4x).
These cover plates are required to prevent people from falling into the
foundation.
Revision: 1.2
Date released: 16-08-2018