HVC 450 kW E-Bus Charger Installation Guide

6. Commissioning

6.1. Commissioning preparation

Commissioning is the last phase necessary to get the HVC 450 kW E-Bus Charger into
operation.
The planning steps for the commissioning phase are shown in the figure below.
D
Commissioning
The commissioning of the HVC 450 kW E-Bus Charger need to be performed by a service
engineer from the ABB Delivery department and/or a certified local ABB service engineer.
Both will need the support from the local contractor.
Before the service engineer can start, the following conditions must be met:
 All installation work is done.
 Grid power is available.
 A local technician is present for assistance and to switch the power on.
 Boom lift available to check all the connections on the pantograph.
 An electric or hybrid bus available to perform the functional tests.
Warranty
It is not permitted to move the whole or parts of the HVC 450 kW E-Bus
Charger after the commissioning. If the whole or parts of the HVC 450
kW E-Bus Charger is moved without contacting the ABB Service
department, the warranty will be considered void.