PLC commissioning
7.3 Loading the project to the PLC
Operator input sequence steps for loading system blocks into the module
1. To load the configuration of the system blocks change to the SIMATIC Manager.
2. Choose in the SIMATIC Manager in the PLC directory, the directory "Blocks > right
Figure 7-15
3. If there is no connection to the destination system, you must confirm in sequence the
You have loaded the PLC program to the PLC; the PLC is in "STOP" mode.
Note
If the PLC is stopped via the SIMATIC Manager, then it also has to be started via the
SIMATIC Manager. Starting via the PLC mode selector is also possible.
Notice
A "NCK Reset" is required for PLC-NCK synchronization.
58
mouse button> Target system > Load" (see figure below), or the symbol "Load".
Loading system blocks
following dialog requests with:
– "OK" for "Check the required sequence of blocks for correct functioning"
– "Yes" for "Do you want to load system data?"
– "Yes" for "Must system data be deleted on the module and replaced by off-line system
data?"
– "No" for "The module is in STOP mode". Do you want to start the module (cold
restart)"?