Installing The Blank Power Supply Slot Cover; Figure 56: Lifting The Locking Handle On The Blank Power Supply Slot Cover - Allied Telesis AT-SB*908 GEN2 Installation Manual

Advanced layer 3 plus modular switch, alliedware plus v5.4.8-0, virtual chassis stacking, chassis, ethernet line card, fan module, ac/dc power supply
Table of Contents

Advertisement

Installing the Blank Power Supply Slot Cover

If you installed only one power supply in the chassis, check that the empty
power supply slot is covered with the blank power supply slot cover
included with the chassis. Do one of the following:
If the chassis has two power supplies or if the empty power supply
is already covered, go to "Installing the Power Cord Retaining
Clips" on page 103.
If a power supply slot is uncovered, continue with the procedure in
this section.
To install the bank power supply slot cover, perform the following
procedure:
1. Lift the locking handle on the bank power supply slot cover. Refer to
Figure 56.
Figure 56. Lifting the Locking Handle on the Blank Power Supply Slot
2. Align the cover in the empty power supply slot and carefully slide it into
the slot. Figure 57 on page 102 shows the cover being installed in the
PSU B slot.
AT-SBx908 GEN2 Installation Guide for Virtual Chassis Stacking
Cover
101