108 Installation checklist
Check that ...
There is an adequately sized protective earth (ground) conductor between the motor and the drive,
and the conductor has been connected to appropriate terminal, and the terminal have been tightened.
(Pull on the conductors to check.). Proper grounding has also been measured according to the regula-
tions.
The motor cable has been connected to the appropriate terminals, the phase order is right, and the
terminals have been tightened. (Pull on the conductors to check.)
The motor cable has been routed away from other cables.
No power factor compensation capacitors have been connected to the motor cable.
The control cables have been connected to the appropriate terminals, and the terminals have been
tightened. (Pull on the conductors to check.)
The supply voltage matches the nominal input voltage of the drive. Check the type designation label.
The voltage setting of the auxiliary voltage transformers (if any) is correct. See the electrical installation
instructions.
If a drive bypass connection will be used: The direct-on-line contactor of the motor and the drive output
contactor are either mechanically or electrically interlocked, ie, cannot be closed simultaneously.
There are no tools, foreign objects or dust from drilling inside the drive.
The area in front of the drive is clean: the drive cooling fan cannot draw any dust or dirt inside.
All shrouds and cover of the motor connection box are in place. Cabinet doors have been closed.
The motor and the driven equipment are ready for start.