Test

Before executing data link, check the CC-Link IE Controller Network board and cables.
Select a test item using the mode setting on the "Parameter setting" screen in the CC IE
Control utility.
The CC-Link IE Controller Network board test has the following six types.
Item
Bus I/F test
H/W test
Board confirmation
Self-loopback test
Circuit test
Network confirmation
Station-to-station test
Communication test
5
- 17
5.5 Test
Test type
Tests the hardware of the bus I/F function of the CC-Link IE
Controller Network board.
Tests the hardware in the CC-Link IE Controller Network
board.
Tests the hardware of the CC-Link IE Controller Network
board alone, including the send/receive circuit of the
transmission system and cables.
Checks the cable connection status, line status, and
parameter setting status of each station from the control
station.
Checks the cable status connected between two stations
(from OUT at the executing station to IN at the target
station).
Checks whether the transient transmission can be routed
correctly between the own station and specified
communication target.
POINT
The test modes are equivalent to offline. The data link cannot be executed if one
station is set to the test mode during data link. Set the mode to "Online" when
performing data link.
Description
Reference
Section 5.5.1
Section 5.5.2
Section 5.5.3
Section 5.5.4
Section 5.5.5
Section 5.5.6

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Q80bd-j71gp21s-sxQ81bd-j71gp21-sxQ81bd-j71gp21s-sx

Table of Contents