Commissioning With The Iop-2 - Siemens SINAMICS G110M Operating Instructions Manual

Distributed converter for simogear geared motors
Hide thumbs Also See for SINAMICS G110M:
Table of Contents

Advertisement

5.4.3

Commissioning with the IOP-2

Condition
The IOP-2 handheld is connected to the converter.
Description
Note
Screens and sequence may vary
The sequence of the commissioning process and the actual screens may vary according to the
following influences:
• The firmware version of the Intelligent Operator Panel 2 (IOP-2)
• The firmware version of the converter being commissioned
• The specific type of converter being commissioned.
In all the scenarios, the IOP-2 will always display the appropriate commissioning screens and
sequence for the converter to which it is connected.
Select Wizards
Select Continue
Distributed converter for SIMOGEAR geared motors
Operating Instructions, 10/2020, FW V4.7 SP13, A5E31298649B AL
Commissioning tools (Page 100)
Select Basic Commissioning
wizard
Select Control Mode
Commissioning
5.4 Quick commissioning
Select Factory Reset (yes or
no)
Select Motor Data
113