Commissioning

4.2 Commissioning with the IOP

4.2
Commissioning with the IOP
Commission the Inverter
The Intelligent Operator Panel (IOP) has been designed to enhance the interface and
communications capabilities of the SINAMICS Inverters.
The IOP is connected to the Inverter using an Optical RS232 cable. It will automatically
recognise the specific Control Unit to which it is connected, and displays only the parameters
and funtionality of the connected Control Unit.
What do you need?
The IOP Handheld Kit is a completed package that contains the necessary items to
commission and configure the Inverter utilizing the Optical Interface. The cable that is
delivered with the IOP Handheld kit is not compatible with the Optical Interface on the
G120D Inverters; the order details of the necessary cable is given below.
● The IOP Handheld Kit - order number: 6SL3255-0AA00-4HA0.
● Optical Cable - order number: 3RK1922-2BP00
Image 4-1
Basic commissioning wizard
The Basic Commissioning wizard detailed below is for Control Units with version 4.4
software or higher.
62
CU240D-2 and CU250D-2 Optical Interfaces
Getting Started, 07/2016, FW V4.7 SP6, A5E38556189B AA