Suzuki Wagon R Manual page 3635

Hide thumbs Also See for Wagon R:
Table of Contents

Advertisement

1B-16 AIR CONDITIONING (OPTIONAL)
7) Loosen suction hose & liquid pipe bolt (4).
8) Loosen cooling unit bolt (1), nut (2) and screw (3) as shown
in figure.
9) Remove cooling unit (5).
Installation
Reverse removal sequence to install cooling unit, noting the fol-
lowing points.
• If cooling unit or evaporator is replaced, pour 25 cc of refrig-
erating oil to compressor suction-side.
• Install uniformly the padding (1) to installation hole.
1
• Evacuate and charge system referring to "Operation Proce-
dure for Charging A/C with Refrigerant" in this section.
• Adjust heater control cable, referring to "Heater Control
Lever Assembly" in Section 1A.
• Enable air bag system, if equipped.
Tightening torque
Liquid pipe mounting bolt (a): 9.0 N·m (0.9 kg-m, 6.5 lb-ft)
(a)
Inspection
Check the following
• Evaporator fins for leakage, blockage and damage.
• Evaporator fitting for leakage.
Clogged evaporator fins should be washed with water, and should
be dried with compressor air.
NOTE:
Be careful not to damage evaporator fins. If evaporator
fin is bent, straighten it by using a screwdriver or pair of
pliers. If any leakage is found from fitting or tube, repair
or replace evaporator.