5. The 3 safety pins must be removed from the stacking mounts so that
the stacking legs can fit into the mounts.
• If upright, remove the pins from the mounts on the bottom projector
• If inverted, remove the 3 safety pins from the mounts on the top pro-
jector
6. With 1 person on each side, lift the top projector on to the bottom
projector, aligning all 3 stacking points between projectors. The legs
(4) should fit inside the stacking mounts.
7. On each stacking mount, turn the adjusting wheel slightly until the
hole in the top portion of the mount lines up with the hole in the stacking leg.
NOTE: You can increase leverage by using a screwdriver in the holes.
8. At each of the 3 stacking points, insert the safety pin fully through the holes in the stacking mounts and
stacking legs. Ensure that each pin is fully inserted to engage the safety lock and secure the projectors
together. Failure to engage the safety lock could cause the projectors to separate and result in injury or death.
9. Before hoisting, firmly tighten the nuts on the 2 rear stacking legs. If you are ready to align the projectors
to one another, leave these nuts slightly loose until after the alignment.
10. Repeat steps 1–9 if stacking a third projector.
2-18
Minimum of 2 people required.
Critical Safety Procedure. Failure to engage the safety lock could cause the
projectors to separate and result in injury or death.
Never stack more than 3 projectors.
J Series 2.0, 2.4 and 3.0 kW User Manual
020-100707-03 Rev. 1 (02-2014)

Advertisement

Table of Contents
loading

This manual is also suitable for:

J 2.0 kwJ 2.4 kwJ 3.0 kw

Table of Contents