1.10.6 Switch Shut-Down Procedures; Figure 53: Intact Vs Defected Power Pin Holders - Mellanox Technologies MSX6536-10R Hardware Installation Manual

648-port infiniband fdr switchx switch platform
Hide thumbs Also See for MSX6536-10R:
Table of Contents

Advertisement

InfiniBand FDR Switch Platform Hardware User Manual
Figure 53.
5. Start with the ejector handles fully open; that is, at 45 degrees to the front panel of the
management.
6. Holding the management by its sides, carefully set the management board into the
chassis.
7. Using only the management ejector handles, slowly slide the board into the chassis
until the hooks reach the vertical bar.
8. Catch the hooks onto the vertical bar of the chassis and push the ejector handle shut.
9. Lock the ejector handles onto the board.

1.10.6 Switch Shut-Down Procedures

To shut down the chassis run the following command twice (once for each MM):
Reload halt [noconfirm]
Mellanox Technologies

Figure 53: Intact vs Defected Power Pin Holders

Pass
Do not apply excessive force to slide in the management board. If you feel resistance,
remove the management and double check both the chassis and management for any
damage.
On switch systems with dual management systems, first connect the cable and configure
the master management module CPU and only then configure the slave. By default the
master CPU is the top management module. For further information on the master and
MLNX-OS®
slave roles, see the
All management modules in the chassis must go through an initial configuration proce-
dure. See the Installation Guide for the initial configuration procedure.
Fail
Software UM section "High Availability".