ProCore Edge
Service / Maintenance
Preventative Maintenance Schedule
The table below describes the preventative maintenance activities for the first
three years of the system.
Verify the following activities after five years:
• Monthly – Fan air flow at the module intake
• Yearly – Power connection torque along the high-current path
• Air Filter Replacement – Not yet available
ProCore
TM
Edge
Component
Description
Output Cables
Three Output
Cable
Connectors
Webasto Charging Systems, Inc.
Maintenance Verification / Action
Examine cables and replace any cable
that exhibits signs of damage (splits,
cracks, tears, exposed conductors, etc.,
or excessive wear, and discoloration.
Examine connectors, and replace any con-
nector that exhibits signs of damage (splits,
cracks, exposed or pitted power pins, etc.),
or excessive wear, and discoloration.
Installation, Operations, Service & Maintenance
Page 65 of 112
Schedule
*
*
*
*
Part Number 5911110 A02
Need help?
Do you have a question about the ProCore Edge and is the answer not in the manual?