Single-phase installation
Three-phase installation
NOTE:
In case of installation of cables with section 10 mm
, the installer must insert the conductors
2
with due accuracy, verifying that they are properly arranged and inserted, i.e. that the copper
of the cable enters completely into the terminal, that the insulating sheath enters the "drop"
of the plastic insert and operating without excessive strain.
14. Perform a pull test to check that the wires are secure.
15. Secure the terminal block with the Philipps screwdriver.