7.5

Procedures Before Operation

1.
IP address setting
Set the IP address of the NZ2FT-GN. ( Page 98 IP address setting switch)
2.
Installation
Attach the NZ2FT system to the DIN rail and install it in a suitable environment. ( Page 36 Installation Environment and
Installation Position of Module, Page 38 Installation)
3.
Wiring
Connect the power cable and Ethernet cable to the NZ2FT-GN. ( Page 45 Wiring of power cable and I/O cable,  Page
46 Ethernet cable)
Connect the I/O cables to the I/O module. ( Page 45 Wiring of power cable and I/O cable)
4.
Master station setting
Register the CC-Link IE TSN profile and set the communication parameters. ( Page 107 Master station setting)
5.
Connection between the Web server and personal computer
Access the NZ2FT-GN Web server via the USB port or the Ethernet port. ( Page 60 Connection with a Personal
Computer)
6.
Remote station setting
Set the parameters of the NZ2FT-GN and I/O module. ( Page 109 NZ2FT-GN and I/O module setting)