6.3 Preparations
Test equipment
The following test equipment is required for the commissioning tests.
1 Single-phase current source
1 Three-phase current source
1 Single-phase voltage source
1 Three-phase voltage source
1 DC power supply
3 Phase angle meter
3 AC ammeter
3 AC voltmeter
1 Time counter, precision timer
1 PC (not essential)
Relay settings
Before starting the tests, it must be specified whether the tests will use the user's settings or the
default settings.
For the default settings, see the following appendixes:
Appendix H Relay Setting Sheet
Visual inspection
After unpacking the product, check for any damage to the relay case. If there is any damage, the
internal module might also have been affected. Contact the vendor.
Relay ratings
Check that the items described on the nameplate on the front of the relay conform to the user's
specification. The items are: relay type and model, AC current and frequency ratings, and
auxiliary DC supply voltage rating.
Local PC
When using a local PC, connect it with the relay via the RS232C port on the front of the relay.
RSM100 software is required to run the PC.
For the details, see the separate volume "PC INTERFACE RSM100".