9 CONFIGURATION MENU
Example, I/O OFF
1.
HEAD, Welding head 1 (master)
2.
TAIL, welding head 2 (slave)
Press 
 Start, for welding head 1 and welding head 2 at the same time.
Welding head 1 starts to weld.
Welding head 2 starts to weld first when the start position for welding head 1 has been
reached (the distance given WELD HEAD OFFSET).
Press 
 stop, for welding head 1 and welding head 2 at the same time.
Welding head 1 stops welding but travel motion continues.
Welding head 2 stops welding when it has reached the point where equipment 1
stopped welding (the distance that is given in WELD HEAD OFFSET).
Welding is complete.
9.3.7
Tandem for Aristo® 1000 power source
Used when welding with two or more welding heads. The welding heads are each controlled
by their own control unit (PEK).
Position the cursor on the TANDEM row and press ENTER. Select ON using the positioning
knob and press ENTER.
The front welding head is selected.
0460 949 474
3.
WELD HEAD OFFSET
- 50 -