4.2 Mounting dimensions of receiver unit and transmitter unit

Mount the receiver unit and the transmitter unit in a place which has ample free space for maintenance and
check as in the figure below (Fig. 4 - 1).
Stack
c
a
b
Flange pipe to mount stack (*5)
*1: When used in an enviroment with high dust, reserve at least 50mm.
*2: When internal gas temperature is high, reserve the distance of 250mm or more. Note that ad-
justable angle range narrows down, so mounting angle of flange pipe to mount stack should be
adjusted accurately.
*3: Secure sufficient space for installation which permits easy operation.
*4: Scaffold will be required for both the receiver unit and the transmitter unit side.
*5: Use the flange provided with the valve where there is a risk of gas injection or where the op-
erator may be exposed to a dangerous situation.
Scaffold (*4)
d
e
Fig. 4-1
- 12 -
a: Inner diameter of 50mm or more
b: 20 to 70mm (*1)
c: Approximately 200 to 250mm (*2)
d: 400mm or more (*3)
e: 500 to 1500mm (*3)