Install The Cabinet On The Foundation; Open The Cable Inlets - ABB Terra HP Generation 3 Installation Manual

Ul 175 kw static dc system
Hide thumbs Also See for Terra HP Generation 3:
Table of Contents

Advertisement

6.2.2

Install the cabinet on the foundation

Preliminary requirements
Procedure
1. Carefully lower the cabinet on the
foundation with a hoisting equipment
or a forklift truck. Refer to section
5.6.1.
2. Make sure that the holes in the cabinet
(A) and the foundation (B) are aligned.
3. Install the fasteners (C) and the
washers.
4. Tighten the fasteners to the correct
torque. For the specification, refer to
section 12.14.
6.2.3

Open the cable inlets

Preliminary requirements
Procedure
1. Open the door. Refer to section 10.1.
2. Loosen the fasteners (A).
3. Move the sliding plates (B) to open the
cable inlets.
9AKK107992A3069-EN | 004
Hoisting equipment or
forklift truck
Torque wrench
Caution: Make sure that
there is no kink in the
cables.
Open spanner
Installation
Four fasteners M16 and
washers
C
A
B
B A
39

Advertisement

Table of Contents
loading

This manual is also suitable for:

Terra hp generation 3 ulTerra hp 3

Table of Contents