Description
This test will initiate switching commands from the CIT and verify proper switching and
LED indications.
Note:
Manual switching test procedure
........................................................................................................................................................................................................................
1
Enter an STS-1 add/drop cross-connection between an equipped Function Unit and the
Main OLIU. Select
Cross-Connection Wizard
........................................................................................................................................................................................................................
2
Select
........................................................................................................................................................................................................................
3
Under
........................................................................................................................................................................................................................
4
Note the Active Path (m1 or m2).
........................................................................................................................................................................................................................
5
Choose
........................................................................................................................................................................................................................
6
Apply
Click
........................................................................................................................................................................................................................
7
Verify that the Active Path: has changed (m1 to m2 or m2 to m1).
........................................................................................................................................................................................................................
8
Repeat
........................................................................................................................................................................................................................
9
Check off the appropriate box in
E
O
N D
........................................................................................................................................................
............................................................................................................................................................................................................................................................
365-372-603R2.0
Issue 1 January 2009
An STS-1 cross-connect is required in order to perform manual switching.
Configuration -> Cross-Connections...
to enter an add/drop cross-connection.
Fault -> Protection Switch...
Path Protection
choose
Switch Type: Manual
.
Step 2
through
Step 7
S
F
T E P S
Path m1-1-1
and click
.
to verify a switch back to the original ring.