5
Wire-wrap the loose end of the office alarm cable to the alarm panel, making connections
as listed in
Alarm Mult
The following steps should be performed when the bottom shelf in the bay will be directly
connected to the office alarms. The cable added in this procedure is to mult office alarms
in a bay to the bottom shelf. In this procedure the bottom shelf is multed to the shelf
immediately above. That shelf is then multed to the shelf above it. Continue until the top
shelf is connected.
Note:
reported, all office alarm cable mults from that shelf to the bottom shelf must be in
place. No shelf should be skipped.
........................................................................................................................................................................................................................
6
Obtain the office alarm mult cable 848589602 for Alcatel-Lucent 1850 TSS-60. Connect
one end to ALM MULT (J14) of the Alcatel-Lucent 1850 TSS-60 shelf. See
"Office alarm cable connections" (p.
........................................................................................................................................................................................................................
7
Route the office alarm mult cable to the side of the bay and connect it to ALM (J13) of the
Alcatel-Lucent 1850 TSS-60 shelf above.See
(p.
3-58).
........................................................................................................................................................................................................................
8
Repeat this procedure for each shelf in the bay (stopping at the top).
........................................................................................................................................................................................................................
9
Check off the appropriate box in
E
O
N D
........................................................................................................................................................
............................................................................................................................................................................................................................................................
365-372-603R2.0
Issue 1 January 2009
Table 3-19, "Office alarm cable assemblies" (p.
In order for office alarms in a shelf (other than the bottom shelf) to be
S
F
T E P S
3-58).
Figure 3-16, "Office alarm cable routing"
"Installation checklist" (p.
Office alarm cable installation
3-60).
Figure 3-15,