6.3 Program management with PCU 50
Open the Program Manager.
Place the cursor on the program whose tool and zero point data
you wish to back up.
Select the "Continue" and "Back Up Data" softkeys.
Select the data you want to back up.
Change the suggested name if you want to.
The name of the originally selected program with extension
"..._TMZ" will be suggested as a name for your tool or zero point
file.
Press the "OK" softkey.
The tool/zero point data will be set up in the same directory in which
the selected program is stored.
If a tool/zero point file with the specified name already exists, this will
now be overwritten with the new data.
Open the Program Manager.
Place the cursor on the tool/zero point data backup that you wish
to re-import.
Select the "Execute" softkey or the "Input" key.
The window "Read in backup data" is opened.
Select the data (tool offset data, magazine loading data, zero
point data, basic work offsets) that you wish to read in.
Press the "OK" softkey.
The data are read in.
Depending on which data you have selected, ShopMill will behave as
follows:
All tool offset data
All data in the tool management system is deleted first. The backup
data is then read in.
All tool offset data used in the program
If at least one of the tools to be read in already exists in the tool
management system, you can choose between the following options.
6
File Management
6-383

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinumerik 840diSinumerik 810d

Table of Contents