Table 25. Configuring the Master Switch - Part I (Continued)
Step
Step 9 adds the member switches as provisioned switches to the master switch. You need to
add one provisioned switch for each member switch to be in the stack.
9
Add the member switches as provisioned switches to the master switch, with the
SWITCH PROVISION command. Assign them unique IDs in the range of 2 to 4. This
example assumes the stack will have three member switches.
awplus(config)# switch 2 provision x950-28
awplus(config)# switch 3 provision x950-28
awplus(config)# switch 4 provision x950-28
Steps 10 to 15 save your changes and reboot the switch.
10
Return to the Privileged Exec mode.
awplus(config)# exit
11
Enter the WRITE command to save your change. If this is the first management
session, the switch adds the configuration file DEFAULT.CFG to flash memory.
awplus# write
Building configuration ...
[OK]
12
Restart the switch with the REBOOT command.
awplus# reboot
reboot system? (y/n):
awplus#
13
Type "Y" for yes.
14
Wait two minutes for the switch to initialize its management software.
15
Check the ID LED in the management panel on the front panel and do one of the
following:
- If the ID LED is displaying the number 1, VCStack is now enabled on the switch. Go
to "Configuring the Master Switch - Part II" on page 148.
- If the ID LED is displaying "0," VCStack is still disabled. Repeat this procedure,
being sure to issue the WRITE command to save your change before resetting the
switch.