Connecting EnerVista 469 Setup to the Relay
Connecting to the
Relay
NOTE
GE Multilin
Now that the communications parameters have been properly configured, the user
can easily connect to the relay.
1.
Expand the Site list by double clicking on the site name or clicking on the «+»
box to list the available devices for the given site (for example, in the "Pumping
Station 1" site shown below).
2.
Desired device trees can be expanded by clicking the «+» box. The following list
of headers is shown for each device:
Device Definitions
Settings
Actual Values
Commands
Communications
3.
Expand the Settings > Relay Setup list item and double click on Front Panel to
open the Front Panel settings window as shown below:
FIGURE 4–5: Main Window After Connection
4.
The Front Panel settings window will open with a corresponding status indicator
on the lower left of the EnerVista 469 Setup window.
5.
If the status indicator is red, verify that the serial cable is properly connected to
the relay, and that the relay has been properly configured for communications
(steps described earlier).
The front panel setpoints can now be edited, printed, or changed according to user
specifications. Other setpoint and commands windows can be displayed and edited
in a similar manner. Actual values windows are also available for display. These
windows can be locked, arranged, and resized at will.
Refer to the EnerVista 469 Setup Help File for additional information about
the using the software.
http://www.GEindustrial.com/multilin
-
Expand the Site List by double
clicking or by selecting the [+] box
Communications Status Indicator
Green = OK, Red = No Comms
469
Motor Management Relay
4–15