Step 4 After the installation is complete, connect a network cable, a VGA cable, or USB devices as
required. Connect the power cables and power on the RH2288 V3.
----End

3.4.2 Installing the Server on Adjustable Guide Rails

Adjustable guide rails apply to a cabinet with a distance of 543.5 mm to 848.5 mm (21.40 in.
to 33.41 in.) between the front and rear mounting bars.
Procedure
Step 1 Install the guide rails.
1.
Issue 32 (2019-03-28)
Lift the RH2288 V3 and move it to the cabinet. This task requires at least two people.
Place the RH2288 V3 onto the guide rails and slide it into the cabinet. See step (1) in
Figure
3-6.
Figure 3-6 Installing the RH2288 V3
When the two mounting ears of the RH2288 V3 come into contact with the mounting
bars on the cabinet, tighten the captive screws on the mounting ears to secure the
RH2288 V3. See step (2) in
Place a guide rail horizontally in the planned position and keep the guide rail in contact
with the mounting bars in the cabinet. Hook the guide rail to the cabinet. See step (1) in
Figure
3-7.
NOTE
The three holes in each mounting ear of a guide rail should be within a 1U mark.