Chapter 4: Installing the Switch on a Table or in an Equipment Rack
108
Figure 53. Example of Attaching the Brackets to the AT-x550-18XSPQm
3. Have another person hold the switch at the desired location in the
equipment rack while you secure it using four standard equipment rack
screws (not provided). Refer to Figure 54.
Figure 54. Installing the Switch in an Equipment Rack
4. Install the other switches of the stack with the appropriate instructions
in this chapter and Chapter 5, "Installing the Switch on a Wall" on page
111.
Switch