Next, connect the FFC W82 to the J8115 on the back of the SLC first, and then assemble the new
SLC according to the SLC replacement procedure in the reverse order. Please make sure to
tighten all the screws and connect all the cables back in place.
Exercise caution when handling the FFCs as they are very fragile.
When installing the FFCs, be careful not to insert them slanted or bend them.
To reconnect the cables and the two-piece
locations as before removing them.
Step 6
Teke over SLC serial port settings
After the replacement of the SLC is completed, turn ON the power switch of the SLC and the
circuit breaker for the power supply of the display unit. Setting information of the SLC which is to
be replaced have been stored at the CCU. Take over those information to the new SLC from the
CCU by conducting the following steps.
6-1.
Click [Menu] -> [Service] -> [Installation] to open the Installation window.
6-2.
Select [System Configuration] in the 1st Classification pane and [Subsystem
Installation] in the 2nd Classification pane.
6-3.
On left below of Edit/Result pane, click to unmark the check box of the Junction
box that has the replaced SLC once, then mark it again. The setting information
will be loaded into the new SLC from the CCU.
For further information, see "Installation Manual 4.4 Subsystem Installation".
Chapter 4 Replacement procedure
W82
GIF
J821
SLC
PS
SS
J8115
terminal blocks, connect them to the same