Commissioning - acceptance tests
5.3 Sequence of an acceptance test
5.3.3
Configuring and performing an acceptance test
Sequence: Performing an acceptance test
1. Enter the required machine data in the "Overview" setting area.
Figure 5-6
2. Press the "First test" softkey.
The "Switch-off signal path" setting area becomes active.
If you do not wish to use this test, in this setting area, activate option "This test type is not
required for this machine". Also in other setting areas you can deactivate the particular test
in the same way.
126
Overview setting area
Function Manual, 10/2015, 6FC5397-3EP40-5BA3
Safety Integrated