Step
3
4
Note:
Close the pinch valves and the pump
heads
Follow the instructions below to close the pinch valves and the pump heads.
Step
1
ÄKTA readyflux Operating Instructions 29175550 AG
Action
Apply a standard plastic sanitary clamp, a disposable ReadyClamp, or a
stainless steel sanitary clamp to the connector assembly for connection.
Repeat for filter and feed bag connections.
Always operate the system with the feed bag connected to feed and reten-
tate lines. Valves closure during E-Stop, run END or power cycle resets the
valves to default open/close positions with a valid flow path centered on feed
bag.
Action
Turn the black levers on the pinch valves 180 degrees to close the safety
locks on all pinch valves:
• 6 valves on the transfer side of the system
• 11 valves on the front of the system
• 4 valves on the permeate side of the system
5 Operation
5.2 Flow kit installation
5.2.3 Install the CFF flow kit