7.2 Preparing a Monitoring Cable

Prerequisites
Preparing a cord end terminal
Figure 7-3
1.
2.
3.
Figure 7-3 Preparing a cord end terminal
(A) Cord end terminal
connector
Preparing an RS485 Monitoring Cable
Figure 7-4
Issue 07 (2022-09-30)
Network cables, cord end terminals, and RJ45 connectors are prepared.
The following tools are prepared:
Wire stripper
Crimping tool
RJ45 crimping tool
Electrician's knife
Insulation tape
shows how to prepare a cord end terminal.
Strip the insulation layer of cable B to expose cable core C.
Put cable core C through cord end terminal A.
Crimp the metal part of cord end terminal A using a crimping tool.
shows how to prepare an RS485 monitoring cable for the ECC collector.
Copyright © Huawei Technologies Co., Ltd.
(B) Insulation layer
7 Appendix
(C) Copper core wire
326

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c10

Table of Contents