FusionModule2000-S Smart Modular Data Center
User Manual
Figure 3-37 Securing a side sealing plate
Step 7 (Optional) Install the LCD on the front aisle door of the smart cooling product.
1.
2.
3.
Issue 07 (2022-09-30)
Install the LCD on the reserved aisle door LCD mounting kit from the front of
the aisle door.
Secure the LCD to the mounting kit at the rear of the aisle door using four
M4x10 screw assemblies.
Reconnect the LCD to the LCD cables reserved on the smart cooling product.