FusionModule2000-S Smart Modular Data Center
User Manual

3.5.1.4 (Optional) Installing a Vertical Ground Bar

Context
Install the vertical ground bar in the IT cabinet closest to the PDF.
Preparations
Tool: Phillips screwdriver
Material: vertical ground bar
Procedure
Step 1 Open the cabinet rear door and use four M4 screws to secure the vertical ground
bar to the right mounting bar.
The specific securing positions are the screw holes in the middle of the 04 U, 14 U, 29 U, and 39
U positions.
Issue 07 (2022-09-30)