Preparations
Tool: Phillips screwdriver
Materials: cable troughs and accessories
Document: cable trough installation position diagram
Procedure
Step 1 Keep a vertical plate of the cable trough flush with the top surface of the cabinet
and clamp the clasps into the mounting holes in the first row counting from the
front door to the rear door.
Issue 07 (2022-09-30)
Figure 3-40 rPDU cable routing on the top of a cabinet
(1) ELV cable trough
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation
(2) Electric cable trough