FusionModule2000-S Smart Modular Data Center
User Manual
Figure 3-12 Connecting bases
Step 13 Screw the floor holders to the bases, as shown by (2) in the preceding figure.
----End
Follow-up Procedure
Check the installation and ensure that adjacent bases are in close contact with
each other and the gap is even.
3.3 Installing Cabinets
Prerequisites
The floor levelness meets engineering requirements.
Context
To position a cabinet, perform the following steps:
1.
2.
3.
Issue 07 (2022-09-30)
Determine the positions for installing the equipment cabinet and smart
cooling product cabinets based on the layout diagram.
Place the equipment cabinet at the correct installation position.
Place other smart cooling product cabinets at the specified positions in
sequence.
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation
47