Huawei FusionModule2000-S User Manual page 96

Smart modular data center
Hide thumbs Also See for FusionModule2000-S:
Table of Contents

Advertisement

FusionModule2000-S Smart Modular Data Center
User Manual
Preparations
Tool: Phillips screwdriver
Materials: PAD mounting support, PAD
Procedure
Step 1 (Optional) If the feet in the lower part of the PAD mounting support are not as
wide as the PAD, adjust the feet, as shown in
1.
2.
3.
Figure 3-57 Adjusting feet
Step 2 Remove the cable hole baffle plate from the PAD mounting kit, as shown by (1) in
Figure
Step 3 Remove the nut from the PAD mounting support and secure the support to the
PAD mounting kit using the nut, as shown by (2) in
Step 4 Route the PAD power cable through the cable hole in the PAD mounting support
and then connect the cable to the PAD, as shown by (3) in
Step 5 Adjust the feet on the top of the PAD mounting support and clamp the PAD to the
PAD mounting support, as shown by (4) in
Issue 07 (2022-09-30)
Loosen the M4x12 screws on the feet (do not remove the screws), as shown
by (1) in
Figure
3-57.
Adjust the feet symmetrically until they are as wide as the PAD, as shown by
(2) in
Figure
3-57.
Tighten the M4x12 screws on the feet, as shown by (3) in
3-58.
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation
Figure
3-57.
Figure
Figure
3-58.
Figure
Figure
3-58.
3-57.
3-58.
85