Installing Smart Busbar Cables; Connecting A Monitoring Cable To The Smart Eth Gateway - Huawei FusionModule2000-S User Manual

Smart modular data center
Hide thumbs Also See for FusionModule2000-S:
Table of Contents

Advertisement

FusionModule2000-S Smart Modular Data Center
User Manual

4.2 Installing Smart Busbar Cables

For details, see the documents delivered with the equipment, the documents
obtained by scanning the QR code, or
4.3 Connecting a Monitoring Cable to the Smart ETH
Gateway
Prerequisites
The smart ETH gateway has been installed.
Context
Figure 4-9
Figure 4-9 Ports on a smart ETH gateway
(1) PWR_IN cascading power
port
(4) PoE_3–4 ports
(7) FE_2 cascading signal port (8) PWR_OUT cascading power
(10) Status indicator
Procedure
Step 1 Take out the ground cable from the smart ETH gateway fitting bag and connect
the cable to the ground screw on the smart ETH gateway.
Step 2 Connect the PWR_OUT port on the smart ETH gateway to the 53.5VDC_OUT1 or
53.5VDC_OUT2 port on the ECC800-Pro using a power cable.
Issue 07 (2022-09-30)
shows the external ports on a smart ETH gateway.
(2) FE_1 cascading signal port (3) PoE_1–2 ports
(5) 48V_OUT1 power output
port
port
Copyright © Huawei Technologies Co., Ltd.
NMW Smart Busbar 2.0 User Manual .
(6) 48V_OUT2 power output
port
(9) BLINK button
4 System Cabling
124