18. Connect each power cord to the power source.
19. Power up the server.
The installation is complete.

Installing the GPU option

Prerequisites
Before installing this option, make sure that you have the following items available:
GPU option kit
T-15 Torx screwdriver
GPU holder for full-length GPU (PN P11529-B21)
If you are installing the GPU with a power requirement higher than 75W, make sure that one of the following is
installed:
ATX 500W non-hot-plug power supply
Flexible slot power supply
Update the server firmware if it is not the latest revision.
Procedure
1.
Back up all server data.
2.
Power down the server.
3.
Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
4.
Disconnect all peripheral cables from the server.
5.
Do one of the following:
Server in rack mode: Remove the server from the rack.
Server in tower mode: Position the tower server for hardware configuration.
6.
Remove the access panel.
7.
Remove the PCI air baffle.
8.
Remove the system air baffle.
9.
Remove the PCI slot blank:
a. Open the PCI slot retainer.
Hardware options installation