Installing The Tower-To-Rack Conversion Kit; Prepare The Server For Rack Installation - HPE ProLiant ML110 Gen10 User Manual

Hide thumbs Also See for ProLiant ML110 Gen10:
Table of Contents

Advertisement

M5 square-hole cage nuts (4)
Rear shipping screws (2)

Installing the tower-to-rack conversion kit

Use the tower-to-rack conversion kit to switch the tower server to rack mode operation. After the kit is installed, complete
in-rack serviceability for all server components is supported.
Procedure
1. Review the rack warnings and cautions.
2. If the server is currently used in tower mode, prepare the server for rack installation.
3. Install the rack rails and server tray.
4. Install the server into the rack.
5. Power up the server.
6. Enable the increased cooling function.

Prepare the server for rack installation

Prerequisites
Before you perform this procedure, make sure that you have a T-15 Torx screwdriver available.
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Disconnect all peripheral cables from the server.
4. Place the server on the side with the access panel facing up.
Hardware options installation