Three Different Ways To Start And Stop A T1 Line Loop-Back On The Site Controller; How Payload Loop-Back Works On The Site Controller - Motorola iDEN Site Controller System Manual

Gen 3
Table of Contents

Advertisement

Gen 3 Site Controller System Manual
Three Different Ways to Start and Stop a T1 Line
Loop-Back on the Site Controller

How Payload Loop-Back Works on the Site Controller

68P80801E30-A 5/1/2002
Remotely Looping Back the T1 Site Controller for BER Testing
Inband Line Loop-Back
A craftsperson inserts a T1 test set into the line going to the site controller.
The test box then sends a loop-up code, consisting of a repeating 00001
pattern, across the entire T1 frame. All 24 DS0s have the data pattern across
them. The site controller detects this pattern and enters loop-back mode.
When the craftsperson is done testing the T1 line, he sends the inband loop-
down code to the site controller. This code is a repeating 001 pattern across
the entire T1 frame. The site controller detects this pattern and quits looping
the T1. Normal operation on the T1 line can now begin.
Front Panel Line Loop-Back Switch
The front panel of the site controller includes a Loop-Back Switch.
Depressing the SEL/LOOP button for more than two seconds causes site
controller to enter line loop-back mode. Depressing the SEL/LOOP button
for two seconds again deactivates the line loop-back.
Line Loop-Back from a ANSI T1.403 Loop-Back
Command on The Facility Data Link
A craftsperson uses a T1 test set and inserts it into the line going to the site
controller. The test box then sends a T1.403, line loop-up, bit-oriented
message on the FDL towards the site controller.
When the craftsperson is done testing the T1 line, he sends a T1.403, line
loop-down, bit-oriented message on the FDL towards the site controller.
The T1.403, line loop-up and down commands transmit on the T1 Extended
Super Frame Facility Data Link. The loop-up, bit-oriented message is
00001110 11111111, with the rightmost bit transmitted first. The
loop-down, bit-oriented message is 00111000 11111111, with the
rightmost bit transmitted first.
A craftsperson inserts a T1 test set into the line to the site controller. The test
box then sends a T1.403, payload loop-up, bit-oriented message on the FDL
towards the site controller.
When the craftsperson is done testing the T1 line, he sends a T1.403,
payload loop-down, bit-oriented message on the FDL towards the site
controller. Normal operation on the T1 line can now begin.
Chapter 6 System Testing
6-21

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents