Figure 3-9. Creating the rail assemblies
6. Install the rail assemblies into the rack (Figure 3-10). Ensure the three holes in the
Figure 3-10. Installing the rail assemblies
3-10
TS2900 Tape Autoloader Setup, Operator, and Service Guide
front of the unit align with the 1U space marked on the vertical rails in Step 2.
Secure the rails to the rack using four flat-head screws
Use both of the two screw locations on the rear of the rack rail (Figure 3-6). Use
the top and middle screw locations on the front of the rack rail (Figure 3-5).
9
7
on each side of the rack.