Acceptance test

Overview
The machine manufacturer is responsible in ensuring that his plant or machine functions
perfectly. As a consequence, after commissioning, the machine manufacturer must check those
functions or have them checked by specialist personnel, which represent an increased risk of
injury or material damage. This acceptance or validation is, for example, also specified in the
European machinery directive and essentially comprises two parts:
• Checking the safety-relevant functions and machine parts.
→ Acceptance test.
• Generate an "Acceptance report" that describes the test results.
→ Documentation.
Supply information for the validation, e.g. the harmonized European standards EN ISO 13849‑1
and EN ISO 13849‑2.
Function description
Acceptance test of the machine or plant
The acceptance test checks whether the safety-relevant functions in the plant or machine
function correctly. The documentation of the components used in the safety functions can also
provide information about the necessary tests.
Testing the safety-related functions includes, e.g. the following:
• Are all safety equipment such as protective door monitoring devices, light barriers or
emergency-off switches connected and ready for operation?
• Does the higher-level control respond as expected to the safety-relevant feedback signals of
the converter?
• Do the converter settings match the configured safety-relevant function in the machine?
Acceptance test of the converter
The acceptance test of the converter is a part of the acceptance test of the entire machine or
plant.
The acceptance test of the converter checks whether the integrated drive safety functions are
set up correctly for the planned safety function of the machine.
Documentation of the converter
The following must be documented for the converter:
• The results of the acceptance test.
• The settings of the integrated drive safety functions.
The documentation must be signed.
Who may perform the acceptance test of the converter?
The following are authorized to perform a converter acceptance test: Only personnel from the
machine manufacturer, who, on account of their technical qualifications and knowledge of the
256
Distributed converter for SIMOGEAR geared motors
Operating Instructions, 10/2020, FW V4.7 SP13, A5E31298649B AL

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents