Reschedule a ControlNet Network That Has Previously

Been Scheduled

If you change a network that has already been scheduled, you must reschedule
the network for the changes to take effect. For example, if you add I/O to an
existing ControlNet network, you must reschedule the network for the I/O to
become active.
1. Start RSNetWorx for ControlNet software.
2. Open the ControlNet file that matches the existing network.
3. Go online.
Configure a ControlNet Module
Publication CNET-UM001C-EN-P - November 2005
3-23