2. Commissioning

2.2.8 Commissioning the CP system on the PROFIBUS-DP

Configuration run
2-34
Please note
Please observe also the switching-on instructions in the
manual for your controller.
Proceed as follows:
1. Connect the field bus cable to the field bus node.
2. Switch on the power supply:
S of all the field bus slaves,
S of the CP system.
3. Switch on the power supply for the master module.
Some master systems automatically carry out a comparison
between the NOMINAL and the ACTUAL configurations
(= DIL switch setting), when you switch on the system.
For this configuration run it is important that:
the specifications for the NOMINAL configuration are com-
plete and correct (see also chapter 2.1.2).
the power supplies for the PLC and the field bus slaves
are switched on either simultaneously or in the sequence
specified below.