2. Commissioning
2.3 Commissioning the CP system on the INTERBUS
PLEASE NOTE
The switching-on instructions in the manual for the
INTERBUS module must also be observed.
Proceed as follows:
1. Connect the INTERBUS cables to the field bus
2. Switch on the operating voltages:
3. Switch on the operating voltage for the master
Configura-
When you switch your controller on, it will automatically
tion run
carry out a comparison between the NOMINAL and AC-
TUAL configurations. For this configuration run it is im-
portant that:
– the specifications for the NOMINAL configuration are
– the power supplies to the PLC and to the field bus
CP FB6-E 9809c
node.
• for all remote bus/installation remote bus slaves,
• for the CP system.
module.
complete and correct.
slaves are switched on either simultaneously or in
the sequence specified above.
The bus is not able to operate until all the bus slaves
are switched on.
2-17