2. Commissioning
2.1
Preparing the CP system for operation on the PROFIBUS-DP
2.1.1 Power supply
2.1.2 Saving the string assignment
Festo P.BE-CP-FB13-E-EN en 0112e
Please note
Supply the CP field bus node separately with operating
voltage via a suitable power unit (see manual "CP system"
and chapter 1.5).
Please note
Before commissioning the CP system, you must first
prepare the CP system for commissioning (see manual "CP
system").
Before commissioning the CP system on the PROFIBUS-DP,
proceed as follows:
1. Connect the power supply for the node (see manual
"CP system")
2. Connect the CP modules
3. Switch on the power supply
4. Save the string assignment by pressing the SAVE button
2-3