9.2.6 Installation instructions

During installation, ensure that the control cables, signal cables (0-10 V,
4-20 mA, 24 V DC, etc.), and the field bus system's (EtherNet/IP) connection
cables are not routed directly parallel to energy-carrying mains connection
cables or motor connection cables. With parallel cable routing, the clearances
between control, signal and field bus cables ② and energy-carrying mains
and motor cables ① must be greater than 30 cm.
Cables should always intersect at right angles.
≧ 300 mm
(≧ 11.81")
Figure 115:
Cable routing for EtherNet/IP ② and mains/motor cables ①
Never lay the cable of a field bus system directly parallel to the
energy carrying cables.
If the system requires a parallel routing in cable ducts, a partition must be
installed between the field bus cable ② and the mains and motor cable ①,
in order to prevent electromagnetic interference on the field bus.
b
b
a
Figure 116:
Separate routing in the cable duct
a Mains and motor connection cable
b EtherNet/IP cable
In all cases only use approved EtherNet/IP cables.
Rapid Link 5 · RAMO5 · RASP5 05/20 MN034004EN www.eaton.com
a
9 Communication
9.2 EtherNet / IP
209

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rapid link ramo5Rapid link rasp5

Table of Contents