4 Operation
4.1 Commissioning checklist
No.
Activity
1
Installation and wiring have been carried out in line with the instruction leaflets
(→ IL034084ZU and IL034085ZU).
2
All wiring and cable remnants and all the tools used have been removed from the proximity of the
RAMO5, RASP5, motor and drive unit.
3
All plug connectors in the power section are made as described in this manual.
→ The ASi bus must be plugged in and powered in manual mode as well.
4
The cables connected to the RAMO5 and RASP5 Rapid Link 5 modules are notshorted and not
connected to ground (PE), except the PE cable.
5
The heat sink is correctly earthed (PE) on the RASP5 speed control unit.
6
All electrical connections on the motor are established correctly.
7
Each single phase of the supply voltage (power bus L1, L2, L3) is protected with a fuse.
8
The RAMO5 and RASP5 Rapid Link 5 modules and the motor are adapted to the mains voltage.
→ Section 1.3, Rating data on the nameplate, page 15, connection type (star, delta) of the motor has
been tested.
9
The quality and volume of cooling air are in line with the environmental conditions required for
RAMO5, RASP5 and the motor.
10
The motor and operating parameters have been set.
11
The effective direction of a coupled machine will allow the motor to start.
12
All emergency stop functions and safety functions are in an appropriate condition.
Before commissioning the RAMO5 and RASP5 Rapid Link 5 modules, check
the following points (checklist):