Place only one server node in an ESD bag.
Step 7 Install filler modules.
Install filler panels in vacant slots. Otherwise, the ventilation, heat dissipation,
electromagnetic shielding, and dustproof effects of the chassis will be affected.
----End
8.3.4 Installing an XH321 V5
Procedure
Step 1 Determine the position of the server node in the chassis.
Figure 8-7 Positions and slot numbers of the XH321 V5 server nodes
Step 2 Remove filler modules.
1.
2.
3.
Issue 07 (2019-12-20)
NO TICE
NO TICE
Install the lower server nodes and then the upper server nodes.
Perform this operation only when filler modules are installed.
Press the ejector release button on the filler module. See (1) in
Fully open the ejector lever. See (2) in
Holding the ejector lever, pull the filler module from the chassis. See (3) in
Figure
8-8.