9 (First) Commissioning

9.1 Requirements

Check the connections
Before starting the commissioning process, ensure that all electrical connections have the
correct polarity and make sure that everything is connected according to the instructions
in chapters 7 "Sunny Island Electrical Connection" (Page 39).
Always save data
Always use the MMC/SD card for saving data and events. This way, in case of a failure,
the SMA Solar Technology AG can help you quickly.
The Quick Configuration Guide (QCG) allows you to quickly install and commission your island
grid system.
On the Sunny Island, choose one of the following positions:
-
Start system
-
New system
-
New battery
Set up the parameters of the desired system specifically.
QCG with Sunny Remote Control 1 only
You can read and set up lists of menus, parameters and errors only with the Sunny
Remote Control 1!
You can start up the Sunny Island without an external display as well. In this case the
Sunny Island works only with the default parameters
(see chapter 8 "Control Elements" (Page 70)).
Technical Description
(First) Commissioning
SI2012_2224-TEN082311
75