8 (First) Commissioning

8.1 Precondition

Before beginning with the commissioning, ensure that all electrical connections
have the correct polarity and make sure that everything is connected according to
the instructions in section 6 "Electrical Connection" (Page 33).
The Quick Configuration Guide (QCG) allows you to quickly and easily commission
your Sunny Island 5048. To do so, use the menu to select the 'right' system for you. The
display then shows a selection, via which the parameters can be set specifically.

8.2 Starting the Quick Configuration Guide (QCG)

When starting the QCG, useful parameter values are set as default settings!
The QCG is automatically activated during the initial startup of the device.
1.
Switch on the Sunny Island 5048 by switching the DC circuit breaker to the "ON"
position.
2.
The Sunny Island 5048 starts the startup phase. Wait for
the following displays.
When starting the Sunny Island 5048 for the first time, the QCG is automatically
activated. Please continue reading in point 6. Otherwise, follow this list.
3.
As soon as the startup phase is finished, the message
"To init system hold <Enter>" is displayed.
4.
Press and hold down <Enter> until the Sunny Island 5048 beeps three times.
Technical Description
(First) Commissioning
SIBFSBOOT V1.000
SMA SMA SMA SMA
SMA SMA SMA
SI5048
@SMA 2006
To init system
hold <Enter>
SI5048-11:EE4206