CHECKING AND ADJUSTING START OF DELIVERY

Governor Impulse Method (RIV)
In order to be able to register the relationship of the
injection pump relative to the engine two signals are
required.
TDC impulse from the crankshaft.
Governor impulse from the injection pump.
Both impulses are supplied by pulse generators.
1 Fuel Injection Pump
2 Rl Sensor
3 Digital Testor
SSANGYONG Y200
DIESEL ENGINE CONTROLS 1F3-31
In order to obtain a measuring signal the sensor pins
must be moved past the pulse generators with a
minimum speed (idle speed). A measuring instrument
measures the time interval of the two impulses,
converting the result into an angular value which is
then indicated.
4 TDC Pluse Sender Unit
5 Battery
YAD1FBF0